Assignment of construction contracts
Assignment is the right to transfer 'choses in action' defined as 'all personal rights of property which can only be claimed or enforced by action and not by taking physical possession'.
This definition includes benefits arising under a construction contract such as right to payment, but not burdens such as the obligation to pay. The definition also includes claims for breach of contract.
A common error is to assume that the right to assign must be agreed as part of a contract, like a novation. Assignment is a unilateral right created by statute, Section 136 of The Law of Property Act 1925 or by the law of equity (law developed by the Chancery Division of the High Court of England and Wales).
Whilst not a contractual right, the right to assign can be excluded, or restricted, by contract, for example, it is common in collateral warranties to restrict to one assignment without the written permission of the warrantor.
Under Section 136 of The Law of Property Act 1925 the formalities required to create an effective legal assignment are:
- An absolute (i.e. not part of a debt or by way of charge only) assignment in writing signed by the assignor.
- A debt or other legal right of action.
- Express notice in writing to the debtor (no particular form of wording is necessary).
An assignment which fails to comply with the above formalities may, nevertheless, still be effective as an equitable assignment. Indeed an equitable assignment may be verbal. There is no substantial difference between legal and equitable assignments (though, of course it will be easier to prove a legal assignment), there are, however, procedural differences.
The assignee of a legal assignment sues the debtor in the assignee's own name. The assignee of an equitable assignment of a legal chose in action or an equitable chose that is not absolute, must join the assignor (as claimant if the assignor agrees, or defendant if not ) into any legal proceedings.
The effect of a legal or equitable assignment is to put the assignee in the same position as the assignor in respect of the benefits (not burdens) arising from the original transaction with the debtor. Consequently:
'... a debt which accrues due before notice of assignment is received, whether or not it is payable before that date, or a debt which arises out of the same contract as that which gives rise to the assigned debt, or is closely connected with that contract, may be set off against the assignee.'
(Ref. Business Computers Ltd v Anglo African Leasing Ltd.)
A counterclaim for unliquidated damages may also be set off by the debtor, but only to the value of the assigned debt. Further when there have been successive assignments the debtor cannot set off against claims by the ultimate assignee, counterclaims which the debtor has against intermediate assignees.
The Scottish law equivalent is assignation.
[edit] Related articles on Designing Buildings
- Alienation covenant.
- Appointing consultants.
- Assignation.
- Assignment of choses in action.
- Assignment of debt.
- Construction contracts.
- Difference between assignment and novation.
- Difference between collateral warranties and third party rights.
- Legal and equitable assignment.
- Novation.
- Novation agreement.
- Privity of contract.
- Privity of title.
- Proprietary information.
- Recovery of third party losses.
- Reliance letter.
- Restrictions on assignment.
- Reverse premium.
- Set off.
- The Contracts (Rights of Third Parties) Act.
- Title.
- Warranty.
[edit] External references
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.

























Comments